Renewable Generators

The database describes 17,523 sites with a capacity of 62,247MW. In the year to the end of March-2026, there were 8,385 of these sites with a capacity of 57,289MW generating approximately 143,123GWh and receiving 108,351,771 ROCs. Data last updated : May-2026. Page 4 of 176 in descending order of RLF.
ID Generator Name Country IC (kW) Technology Subsidy Accreditation Commissioned RLF
ALF Latest Latest MWh p.a.
R00077RJEN Todhills Power EN 1,330 Landfill Gas RO 2002-04-01 2000-06-01 70.3% 26.2% 2026‑03 3,056
R00095RJEN Rainham Phase II EN 12,956 Landfill Gas RO 2002-04-01 2000-04-01 70.2% 58.4% 2026‑02 66,256
R00460RJEN Bramford Landfill Site EN 650 Landfill Gas RO 2004-04-01 2004-04-01 70.2% 43.7% 2026‑02 2,487
R00117RAEN Smerrill Generating Station EN 306 Anaerobic Digestion RO 2008-09-11 2008-09-11 69.8% 73.1% 2026‑03 1,960
R00057RJEN Mayton Wood EN 1,888 Landfill Gas RO 2002-04-01 1996-02-01 69.6% 65.7% 2026‑03 1,898
R00025RJEN Milton Landfill EN 2,136 Landfill Gas RO 2002-04-01 1993-07-01 69.6% 66.4% 2026‑03 12,416
R00595RJEN Harewood Whin extension EN 3,908 Landfill Gas RO 2009-04-06 2009-04-06 69.6% 63.0% 2026‑03 8,283
G01555HYWA Bryn Cowlyd WTW Hydroturbine WA 550 Hydro FiT 2018-02-01 2018-02-01 69.5% 38.1% 2026‑01 1,835
R00009RJEN Llandulas Landfill Site EN 3,400 Landfill Gas RO 2002-04-01 1999-07-01 69.5% 24.7% 2026‑03 4,333
R00024NANI Lisahally Power Station NI 36,310 Dedicated biomass RO 2015-07-23 2015-07-23 69.4% 36.1% 2026‑02 114,882
R00476RAEN Linton Mill CHP EN 200 Advanced Gasification RO 2017-03-28 2017-03-28 69.3% 66.7% 2026‑02 1,168
G01606BWEN Fraddon Biogas Limited EN 249 Anaerobic Digestion FiT 2014-12-03 2014-12-03 69.3% 80.2% 2026‑01 1,749
R00005SASC Stevens Croft - A, B, C, D, E, (01/06/07) SC 50,725 Dedicated biomass RO 2007-11-08 2007-11-08 69.1% 83.8% 2026‑02 372,387
G00714BWWA Pencefn AD WA 200 Anaerobic Digestion FiT 2016-07-26 2016-07-26 69.0% 78.9% 2026‑04 1,382
G01525HYEN Errwood Reservoir EN 100 Hydro None 2016-11-21 2016-11-21 69.0% 54.1% 2026‑03 474
G01606HYSC Clachan Hydro SC 50 Hydro FiT 2013-11-26 2013-11-26 68.9% 98.9% 2026‑03 433
R00165RXEN Lough CHP EN 49 Standard Gasification RO 2017-02-07 2017-01-31 68.8% 88.0% 2026‑03 378
R00138RREN Kidderminster STW - A,C,D EN 625 Sewage Gas RO 2004-12-01 2004-12-01 68.8% 60.7% 2026‑02 3,325
R00120RREN Spernal (Redditch) STW - D EN 851 Sewage Gas RO 2004-05-01 2004-05-01 68.8% 42.9% 2026‑03 3,195
R00147RAEN Blackburn Meadows Renewable Energy Plant EN 34,000 Dedicated biomass RO 2014-06-24 2014-06-24 68.7% 76.6% 2026‑02 228,091
R00214RREN Bexhill WTW EN 772 Sewage Gas RO 2013-03-28 2013-03-28 68.7% 50.1% 2026‑03 3,387
R00045SJSC Easter Langlee SC 800 Landfill Gas RO 2009-04-24 2009-04-24 68.7% 40.9% 2026‑03 1,434
R00089RJEN Wapseys Wood Landfill (generation Phase 1) EN 6,764 Landfill Gas RO 2002-04-01 1987-07-01 68.7% 25.4% 2026‑03 10,585
R00047RAWA Tynddol Gassifier WA 102 Advanced Gasification RO 2017-03-28 2016-10-19 68.7% 63.9% 2026‑02 559
G01377BWEN Copys Green EN 170 Anaerobic Digestion FiT 2010-06-25 2010-06-21 68.7% 56.0% 2026‑04 834
R00005SESC Trinafour Power Station - A SC 550 Hydro RO 2002-04-01 1959-01-01 68.6% 24.0% 2026‑02 1,158
G01910HYSC River Pattack Hydro Scheme SC 2,000 Hydro None 2017-08-17 2017-08-17 68.6% 75.7% 2026‑03 13,269
R00532RJEN Colnbrook Gas To Energy EN 3,158 Landfill Gas RO 2005-09-01 2005-09-01 68.6% 37.2% 2026‑02 10,280
R00363RAEN SpannerCHP EN 90 Advanced Gasification RO 2016-03-29 2016-03-28 68.6% 52.7% 2026‑03 416
G02001BWEN Wardley Biogas Limited EN 499 Anaerobic Digestion FiT 2020-03-20 2020-03-20 68.5% 34.1% 2026‑01 1,489
R00350RAEN Gorsey Advance Gasification EN 199 Advanced Gasification RO 2015-12-08 2015-12-03 68.4% 75.2% 2026‑01 1,310
R00202RAEN Sleaford REP EN 45,000 Dedicated biomass RO 2014-08-01 2014-08-01 68.3% 74.8% 2026‑01 294,843
R00002RAWA Western Wood Energy Plant A WA 16,400 Dedicated biomass RO 2008-07-03 2008-07-01 68.3% 59.8% 2026‑02 85,881
R00002NJNI Cottonmount NI 3,136 Landfill Gas RO 2009-02-10 2009-02-10 68.3% 74.1% 2026‑02 20,359
R00200RJEN Ulnes Walton Energy EN 2,000 Landfill Gas RO 2002-04-01 2002-03-01 68.2% 44.6% 2026‑03 2,578
R00441RJEN Humberfield Landfill EN 3,144 Landfill Gas RO 2003-08-01 2003-08-01 68.2% 61.9% 2026‑03 5,679
R00512RJWA Pwllfawatkin Generation - A,E WA 3,240 Landfill Gas RO 2005-09-01 2005-09-01 68.2% 37.0% 2026‑03 3,452
R00089REWA CWM Rheidol Comp Set (Gen7) - A WA 100 Hydro RO 2003-10-01 1985-04-01 68.1% 15.6% 2026‑03 137
G02019HYSC Lower Glenedvon Hydro Scheme (rev 2) SC 75 Hydro FiT 2020-10-28 2020-10-28 68.1% 60.1% 2026‑03 395
R00522RAEN Normans Gas & Power EN 360 Anaerobic Digestion RO 2017-03-31 2017-03-30 68.0% 23.6% 2026‑03 743
R00050SDSC Twin Lochs Hydro - A SC 500 Hydro RO 2003-08-01 2003-08-01 67.9% 69.0% 2026‑02 3,024
R00110NANI Rea Hill CHP NI 500 Anaerobic Digestion RO 2017-03-21 2017-03-21 67.9% 63.7% 2026‑02 2,792
R00215RREN Ford WTW EN 772 Sewage Gas RO 2013-09-13 2013-09-13 67.9% 49.6% 2026‑03 3,355
R00007RAEN Thetford Power Station (RA) - A B EN 44,200 Dedicated biomass RO 2002-04-01 1998-10-01 67.9% 64.2% 2026‑02 248,398
G01630HYSC Camps Reservoir SC 65 Hydro FiT 2014-02-10 2014-02-10 67.9% 65.5% 2026‑04 373
R00172NANI Milfordbiogas NI 235 Anaerobic Digestion RO 2017-03-31 2017-03-23 67.8% 72.3% 2026‑02 1,489
R00552RJEN Skelton Grange - A, C EN 6,331 Landfill Gas RO 2007-01-01 2006-11-01 67.8% 49.1% 2026‑02 22,669
R00254RAEN Brigg REP EN 54,635 Dedicated biomass RO 2015-10-20 2015-10-20 67.8% 70.0% 2026‑02 288,575
R00178RJEN Compton Bassett Landfill EN 2,348 Landfill Gas RO 2002-05-01 2002-05-01 67.7% 59.9% 2026‑03 10,866
R00646RJEN Sugden End Energy EN 150 Landfill Gas RO 2016-04-03 2015-01-29 67.7% 55.6% 2026‑03 730
R00017RJEN Wingmoor Landfill (Infinis) EN 2,809 Landfill Gas RO 2002-04-01 1996-03-01 67.6% 48.5% 2026‑03 11,926
R00146RXEN Elms Green Biomass CHP 3 EN 45 Standard Gasification RO 2016-05-20 2016-05-18 67.6% 60.0% 2026‑02 237
G01802BWEN JFS & Associates - New Mill Biogas EN 2,000 Anaerobic Digestion FiT 2016-09-14 2016-09-14 67.6% 51.6% 2026‑03 9,047
G01674HYSC Borla Hydro SC 50 Hydro FiT 2014-12-03 2014-12-03 67.6% 65.3% 2026‑03 286
G01459BGSC Rosehill Timber SC 98 Anaerobic Digestion None 2022-06-27 2018-03-31 67.6% 70.6% 2026‑04 606
R00224RREN Slough STW CHP 2015 EN 1,262 Sewage Gas RO 2016-05-17 2016-05-17 67.5% 72.7% 2026‑03 7,640
R00069SASC Cardryne CHP SC 130 Advanced Gasification RO 2017-03-29 2017-03-22 67.5% 55.3% 2026‑02 629
R00034RJEN Brogborough Phase III EN 16,638 Landfill Gas RO 2002-04-01 2001-02-01 67.4% 28.4% 2026‑03 41,359
R00106REWA Brenig NFFO Site MANW. 570.98 WA 60 Hydro RO 2008-07-10 2008-04-01 67.4% 67.5% 2026‑02 355
R00113RREN Southern Water Canterbury CHP - D EN 360 Sewage Gas RO 2004-04-01 2004-04-01 67.3% 46.1% 2026‑03 1,453
G01799BWEN Olleco CHP Aylesbury EN 1,500 Anaerobic Digestion FiT 2016-08-16 2016-08-16 67.3% 60.0% 2026‑02 7,881
G01501BWEN May Farm Anaerobic Digestion Facility EN 3,143 Anaerobic Digestion FiT 2013-08-15 2013-08-15 67.2% 71.5% 2026‑03 19,680
R00457RAEN MEPALCHP EN 14,466 Anaerobic Digestion RO 2017-03-17 2017-03-13 67.1% 81.3% 2026‑02 102,999
R00508RJEN Salt Ayre Power - A,C EN 1,136 Landfill Gas RO 2005-09-01 2005-09-01 67.0% 45.0% 2026‑02 4,476
R00449RJEN Brenkley Landfill EN 2,272 Landfill Gas RO 2003-12-01 2003-12-01 67.0% 37.9% 2026‑03 1,095
R00216RREN Sandown WTW EN 360 Sewage Gas RO 2013-05-07 2013-05-07 66.9% 62.0% 2026‑03 1,954
DRX Drax CfD Unit 1 EN 645,000 Dedicated biomass CfD 2016-12-21 66.9% 86.7% 2026‑03 4,895,650
G01563HYEN Wendron2 EN 35 Hydro FiT 2019-04-24 2019-04-24 66.8% 65.2% 2026‑02 200
R00100RJEN Rainham Landfill EN 4,074 Landfill Gas RO 2002-04-01 2000-02-01 66.8% 52.1% 2026‑02 18,593
R00160RXEN lime-circle chp EN 50 Standard Gasification RO 2016-10-05 2016-06-24 66.8% 54.4% 2026‑04 238
R00170RXEN Barnsley Lane MIcrogeneration EN 65 Landfill Gas RO 2017-03-20 2017-03-17 66.7% 62.5% 2026‑01 356
R00574RJEN Cowpen Bewley EN 2,572 Landfill Gas RO 2008-06-04 2008-06-04 66.7% 40.5% 2026‑03 5,580
R00179RJEN Brookhurst Wood Gas to Energy - A,D EN 3,090 Landfill Gas RO 2002-04-01 2000-12-01 66.6% 37.3% 2026‑02 4,370
R00144RXEN Elms Green Biomass CHP 1 EN 45 Standard Gasification RO 2016-05-18 2016-05-18 66.6% 64.1% 2026‑04 253
G01558BWEN Manor Farm Community Renewables EN 499 Anaerobic Digestion FiT 2014-08-13 2014-08-13 66.6% 87.3% 2026‑03 3,815
R00124RXEN Docking 2 EN 65 Landfill Gas RO 2014-10-14 2014-10-14 66.5% 66.3% 2026‑02 378
R00463RJEN Jameson Road Energy EN 1,625 Landfill Gas RO 2004-07-23 2004-07-23 66.5% 76.4% 2026‑02 7,131
R00165RREN Blackburn CHP WTWW (6/07/07) - A, D EN 1,151 Sewage Gas RO 2007-07-01 2007-01-01 66.4% 75.7% 2026‑02 7,632
R00067RJEN Whinney Hill Landfill Gas EN 6,356 Landfill Gas RO 2002-04-01 1999-01-01 66.4% 92.1% 2026‑02 51,279
R00094RJEN Waverley Wood Farm EN 988 Landfill Gas RO 2002-04-01 1996-06-01 66.4% 50.1% 2026‑02 2,896
R00059RJEN Dogsthorpe EN 1,976 Landfill Gas RO 2002-04-01 1995-09-01 66.4% 56.0% 2026‑03 4,904
G01583BWEN JFS Westholme Farm Biogas Limited EN 499 Anaerobic Digestion FiT 2014-11-03 2014-11-03 66.4% 90.3% 2026‑03 3,945
G01658HYSC Stronchullin Energy Ltd SC 99 Hydro FiT 2014-09-29 2014-09-29 66.4% 70.6% 2026‑04 612
G01962HYSC Lochaber hydro station 1 SC 86,500 Hydro None 2019-05-08 2011-11-14 66.3% 58.6% 2026‑01 443,866
R00046SASC Mains of Fortrie CHP SC 80 Advanced Gasification RO 2016-10-19 2016-06-29 66.3% 52.5% 2026‑02 368
R00518RJEN Gainsborough Generation - A EN 330 Landfill Gas RO 2005-11-01 2005-11-01 66.3% 35.3% 2026‑03 619
G01937HYSC Lussa Compensation Set SC 230 Hydro None 2017-09-01 2017-09-01 66.2% 85.1% 2026‑02 1,714
R00009RXWA Trehir 2 - Full WA 60 Landfill Gas RO 2015-12-17 2015-12-17 66.1% 41.3% 2026‑02 217
R00001RJEN Burntstump EN 1,920 Landfill Gas RO 2002-04-01 1999-04-15 66.1% 59.0% 2026‑03 1,707
R00029RDEN Saddleworth Community Hydro EN 55 Hydro RO 2014-09-08 2014-07-31 66.1% 59.9% 2026‑03 289
R00680NQNI SP2045 NI 250 On-shore wind RO 2018-03-31 2018-03-31 66.0% 68.2% 2026‑03 1,493
R00381RAEN Snetterton Renewable Energy Plant EN 49,458 Dedicated biomass RO 2016-12-13 2016-12-13 66.0% 81.7% 2026‑02 353,880
C00083RAEN Drax Biomass Conversion EN 1,935,000 Dedicated biomass RO 2003-03-01 1974-01-01 66.0% 58.8% 2026‑01 9,967,530
G01697BWEN Old Court 2 EN 200 Anaerobic Digestion FiT 2015-09-22 2015-09-22 66.0% 84.5% 2026‑04 1,481
R00006SJSC Auchencarroch Landfill SC 2,012 Landfill Gas RO 2002-04-01 2002-04-01 65.9% 51.7% 2026‑02 9,113
R00213RJEN Calvert Phase Ii EN 30,611 Landfill Gas RO 2002-12-01 2002-12-01 65.5% 19.8% 2026‑03 40,901
R00083SESC Kilmelford Power Station - A, C, SC 2,500 Hydro RO 2004-09-01 1956-01-01 65.3% 25.8% 2026‑02 5,643
G01686HYSC Crofthead Hydroelectricity limited SC 98 Hydro FiT 2015-03-13 2015-03-13 65.3% 70.7% 2026‑03 607
R00007SASC Balcas Biomass CHP Power Station SC 9,600 Dedicated biomass RO 2009-10-11 2009-10-11 65.2% 53.9% 2026‑03 45,309
R00005RAEN Glanford Power Station (Fibrogen) - A,B EN 16,700 Dedicated biomass RO 2002-04-01 1993-11-01 65.2% 57.6% 2026‑02 84,310