Renewable Generators

The database describes 17,523 sites with a capacity of 62,247MW. In the year to the end of March-2026, there were 8,385 of these sites with a capacity of 57,289MW generating approximately 143,123GWh and receiving 108,351,771 ROCs. Data last updated : May-2026. Page 4 of 176 in descending order of ALF.
ID Generator Name Country IC (kW) Technology Subsidy Accreditation Commissioned RLF ALF
Latest Latest MWh p.a.
G01999HYSC Deanston New Hydro 2019 SC 350 Hydro FiT 2021-03-23 2021-03-23 55.2% 72.0% 2026‑03 2,207
R00040SJSC Patersons Quarries Generating Station - A SC 4,252 Landfill Gas RO 2006-11-01 2006-11-01 79.2% 72.0% 2026‑03 26,816
R00022RJEN Walpole Landfill EN 1,740 Landfill Gas RO 2002-04-01 1997-02-01 77.4% 71.9% 2026‑03 10,356
G01580BWEN Hilliam Lane Farm EN 1,099 Anaerobic Digestion FiT 2014-11-14 2014-11-14 54.1% 71.9% 2026‑04 6,923
R00032RAWA Barlands CHP 2016 WA 180 Advanced Gasification RO 2016-10-06 2016-10-06 75.0% 71.8% 2026‑03 1,132
R00017SESC Clatto Treatment Works - D SC 350 Hydro RO 2002-04-01 1994-08-01 45.2% 71.7% 2026‑03 1,074
R00050SASC Blackstoun Home Farm CHP SC 98 Standard Gasification RO 2017-02-01 2016-11-09 31.5% 71.6% 2026‑02 614
G01456BWEN Piddlehinton AD Facility EN 1,598 Anaerobic Digestion FiT 2012-06-21 2012-06-21 83.1% 71.6% 2026‑03 10,026
G01511LGEN Bletchley Phase V EN 2,130 Landfill Gas None 2023-06-19 2023-04-06 77.3% 71.5% 2026‑03 13,337
G01454HYWA Ceunant Hydro WA 34 Hydro FiT 2015-08-21 2015-08-21 44.3% 71.5% 2026‑03 213
G01501BWEN May Farm Anaerobic Digestion Facility EN 3,143 Anaerobic Digestion FiT 2013-08-15 2013-08-15 67.2% 71.5% 2026‑03 19,680
R00222RREN Camberley STW CHP 2015 EN 600 Sewage Gas RO 2016-05-04 2016-05-04 54.9% 71.5% 2026‑03 3,760
R00022NANI BH Energy - Biogas NI 500 Anaerobic Digestion RO 2012-01-17 2012-01-17 84.2% 71.4% 2026‑02 3,127
R00146SESC Glen Finglas Turbine SC 460 Hydro RO 2008-04-01 1965-01-01 74.1% 71.3% 2026‑03 2,873
R00116RREN Southern Water East Worthing CHP - D EN 360 Sewage Gas RO 2004-06-01 2004-06-01 72.3% 71.3% 2026‑03 2,247
G01728HYSC Loch Spallander Hydro Scheme SC 96 Hydro FiT 2015-11-06 2015-11-06 73.6% 71.1% 2026‑03 598
G00698BWWA Glanmeheli AD WA 499 Anaerobic Digestion FiT 2015-09-25 2015-09-25 86.0% 71.0% 2026‑03 3,103
G01089BWSC Strathendrick Biogas SC 1,100 Anaerobic Digestion None 2014-03-10 2014-03-10 72.3% 71.0% 2026‑03 6,846
R00122RJEN Ockendon 'A' Power Plant EN 5,250 Landfill Gas RO 2002-04-01 1992-11-01 75.4% 71.0% 2026‑02 32,343
R00006SRSC Hatton CHP (6/11/2007) SC 501 Sewage Gas RO 2008-02-01 2008-02-01 51.6% 70.9% 2026‑02 3,112
R00591RJEN Staple Quarry EN 1,333 Landfill Gas RO 2009-01-15 2009-01-15 73.0% 70.8% 2026‑03 8,271
R00023RJEN Wapseys Wood II EN 2,012 Landfill Gas RO 2002-04-01 1999-01-01 81.0% 70.8% 2026‑03 12,473
G01686HYSC Crofthead Hydroelectricity limited SC 98 Hydro FiT 2015-03-13 2015-03-13 65.3% 70.7% 2026‑03 607
G01658HYSC Stronchullin Energy Ltd SC 99 Hydro FiT 2014-09-29 2014-09-29 66.4% 70.6% 2026‑04 612
G01459BGSC Rosehill Timber SC 98 Anaerobic Digestion None 2022-06-27 2018-03-31 67.6% 70.6% 2026‑04 606
R00475RAEN Biopower Hartlepool EN 5,098 Anaerobic Digestion RO 2017-03-28 2017-03-23 54.5% 70.5% 2026‑01 31,503
R00547RAEN Roundhill FWAD Plant EN 851 Anaerobic Digestion RO 2017-03-31 2017-03-22 72.7% 70.1% 2026‑01 5,223
R00254RAEN Brigg REP EN 54,635 Dedicated biomass RO 2015-10-20 2015-10-20 67.8% 70.0% 2026‑02 288,575
R00032SXSC Piperdam Golf Club CHP SC 49 Standard Gasification RO 2016-10-31 2016-10-04 71.2% 70.0% 2026‑02 301
R00023SXSC Parkview CHP SC 49 Standard Gasification RO 2016-03-31 2016-03-31 62.6% 69.9% 2026‑03 300
R00087NANI CARHILL FARMS BIOGAS NI 330 Anaerobic Digestion RO 2016-10-06 2016-10-06 84.3% 69.7% 2026‑03 2,016
R00640NQNI WLD NI 226 On-shore wind RO 2016-10-01 2016-10-01 37.7% 69.7% 2026‑03 1,374
G01563BWEN JFS Howla Hay Biogas Ltd EN 250 Anaerobic Digestion FiT 2014-08-13 2014-08-13 75.4% 69.7% 2026‑03 1,526
R00357RAEN Templeborough Biomass Power Plant EN 48,960 Dedicated biomass RO 2018-07-10 2018-07-10 59.0% 69.6% 2026‑02 298,509
R00487RAEN S & P - Bay Farm Engine EN 499 Anaerobic Digestion RO 2017-03-29 2017-03-13 73.4% 69.4% 2026‑03 3,034
R00031RAEN Maple Lodge STW (RB) - A, C, D, E EN 3,120 Sewage Gas RO 2006-04-01 1989-01-01 53.3% 69.3% 2026‑02 18,926
R00079RJEN Kibblesworth Landfill EN 3,000 Landfill Gas RO 2002-04-01 1998-11-01 73.5% 69.3% 2026‑03 2,003
R00544RJEN Springfield Farm Landfill Generation - A,C EN 4,250 Landfill Gas RO 2006-10-01 2006-09-01 55.9% 69.2% 2026‑02 23,589
R00562RJEN Bletchley Power Station 2 (6/6/2007) - A EN 6,525 Landfill Gas RO 2007-06-01 2007-04-01 74.3% 69.1% 2026‑03 39,518
R00105NANI MillfordAD NI 260 Anaerobic Digestion RO 2017-01-27 2017-01-27 76.3% 69.1% 2026‑01 1,573
LYN Lynemouth Power Station EN 420,000 Dedicated biomass CfD 2019-04-01 2018-06-23 52.7% 69.1% 2026‑03 2,542,340
R00185RXEN Morningthorpe Landfill EN 50 Landfill Gas RO 2017-03-30 2017-03-21 78.1% 69.0% 2026‑02 302
R00050SDSC Twin Lochs Hydro - A SC 500 Hydro RO 2003-08-01 2003-08-01 67.9% 69.0% 2026‑02 3,024
R00389RAEN Hilltop EN 199 Advanced Gasification RO 2016-09-28 2016-09-27 63.4% 69.0% 2026‑02 1,203
G01417BWEN Doncaster AD plant EN 4,964 Anaerobic Digestion FiT 2011-11-08 2011-11-08 62.9% 68.9% 2026‑02 29,973
R00267NQNI Flack Micon NI 235 On-shore wind RO 2014-09-23 2014-09-23 44.5% 68.8% 2026‑04 1,416
R00451RJEN Sutton Courtney - NFFO5 EN 7,455 Landfill Gas RO 2003-10-01 2003-10-01 78.5% 68.8% 2026‑03 44,903
R00006RJEN Aveley Landfill EN 3,840 Landfill Gas RO 2002-04-01 1999-07-01 59.4% 68.7% 2026‑03 6,040
R00388RAEN Railway EN 199 Advanced Gasification RO 2016-09-28 2016-09-27 63.5% 68.6% 2026‑02 1,196
R00543RJEN Poplars Landfill Phase 4 - A, C EN 3,900 Landfill Gas RO 2006-08-01 2006-08-01 78.2% 68.5% 2026‑03 18,086
R00565RJEN Brogborough Phase V - A, C EN 11,000 Landfill Gas RO 2007-07-01 2007-07-01 47.0% 68.4% 2026‑03 31,452
R00002SRSC Nigg Bay WWTW - A,C,D SC 1,840 Sewage Gas RO 2005-08-01 2002-04-01 47.7% 68.4% 2026‑03 11,031
G01690HYSC Druimdrishaig Hydro Scheme SC 1,000 Hydro None 2015-03-27 2015-03-27 62.5% 68.3% 2026‑04 5,984
R00262RAEN Emerald Biogas EN 2,760 Anaerobic Digestion RO 2013-03-28 2013-03-28 64.0% 68.3% 2026‑02 16,523
R00680NQNI SP2045 NI 250 On-shore wind RO 2018-03-31 2018-03-31 66.0% 68.2% 2026‑03 1,493
R00143RREN Hayden STW EN 499 Sewage Gas RO 2005-02-01 2005-02-01 64.6% 68.2% 2026‑03 2,979
R00016RREN Oldham CHP at Oldham WWTW - A,C,D EN 1,274 Sewage Gas RO 2002-04-01 1991-08-01 42.8% 68.2% 2026‑02 7,612
R00140NANI Greenville Energy - Cherry Pipes Dungannon NI 334 Anaerobic Digestion RO 2017-03-31 2017-03-31 41.4% 68.1% 2026‑03 1,992
G00003HPSC Blackwater SC 790 Hydro FiT 2021-11-25 2021-11-25 61.6% 68.1% 2026‑03 4,711
R00022SASC energen biogas cumbernauld SC 5,822 Anaerobic Digestion RO 2011-06-22 2011-06-22 62.3% 67.9% 2026‑03 34,631
R00542RJEN Kenwick Generation - A,E EN 1,065 Landfill Gas RO 2005-09-01 2005-09-01 36.5% 67.8% 2026‑03 600
R00442RAEN Kent Renewable Energy EN 33,190 Dedicated biomass RO 2018-04-21 2018-04-21 59.4% 67.8% 2026‑02 197,183
R00177RAEN Bio Power One EN 17,450 Dedicated biomass RO 2011-09-16 2011-09-16 63.6% 67.8% 2026‑02 103,624
R00016SESC Kinlochleven Hydro Power Station, G SC 23,500 Hydro RO 2002-04-01 1909-01-01 87.2% 67.7% 2026‑02 139,376
R00017RXWA Rogers Biomass CHP WA 35 Dedicated biomass RO 2017-01-13 2016-11-21 34.5% 67.6% 2026‑03 207
R00228RREN Mogden STW 2016 EN 6,000 Sewage Gas RO 2017-02-21 2017-02-21 78.2% 67.6% 2026‑03 35,524
R00106REWA Brenig NFFO Site MANW. 570.98 WA 60 Hydro RO 2008-07-10 2008-04-01 67.4% 67.5% 2026‑02 355
G01403BWEN Clayton Hall Farm Bioenergy EN 1,000 Anaerobic Digestion FiT 2011-03-25 2011-03-02 57.3% 67.2% 2026‑04 5,882
G01503LGEN Bletchley Phase IV EN 2,113 Landfill Gas None 2014-11-13 2014-11-05 56.0% 66.9% 2026‑03 12,375
R00408NQNI Ballure NI 226 On-shore wind RO 2014-10-23 2014-10-23 34.4% 66.9% 2026‑04 1,318
R00058SESC Shin Power Station-A,G SC 18,640 Hydro RO 2003-06-01 2003-06-01 76.8% 66.9% 2026‑02 109,128
G01545HYEN Thirlmere Hydro Station EN 14 Hydro None 2017-08-17 2017-08-17 38.9% 66.8% 2026‑03 82
G01587BWEN Horseway Energy Ltd EN 499 Anaerobic Digestion FiT 2014-12-02 2014-12-02 60.8% 66.8% 2026‑03 2,920
R00002SDSC New Lanark Mills - D SC 500 Hydro RO 2002-04-01 1994-05-01 54.0% 66.8% 2026‑03 2,927
R00476RAEN Linton Mill CHP EN 200 Advanced Gasification RO 2017-03-28 2017-03-28 69.3% 66.7% 2026‑02 1,168
R00154RJEN Newton Longville EN 988 Landfill Gas RO 2002-04-01 1995-11-01 79.9% 66.6% 2026‑03 5,761
R00539RJEN Blackborough End (2) - A EN 1,048 Landfill Gas RO 2006-08-01 2006-08-01 45.3% 66.5% 2026‑03 6,106
R00043RAWA Syrior Farm CHP WA 90 Advanced Gasification RO 2017-03-16 2017-03-08 74.9% 66.5% 2026‑02 524
R00025RJEN Milton Landfill EN 2,136 Landfill Gas RO 2002-04-01 1993-07-01 69.6% 66.4% 2026‑03 12,416
R00055SASC Auchencheyne CHP SC 133 Advanced Gasification RO 2017-03-09 2017-01-20 58.2% 66.3% 2026‑03 773
R00088RJEN Station Farm Landfill EN 2,050 Landfill Gas RO 2002-04-01 1999-10-01 55.6% 66.3% 2026‑03 10,344
R00124RXEN Docking 2 EN 65 Landfill Gas RO 2014-10-14 2014-10-14 66.5% 66.3% 2026‑02 378
R00585RAEN GEN0179977_2 EN 1,500 Anaerobic Digestion RO 2010-08-31 2010-08-31 77.5% 66.3% 2026‑02 8,714
R00233NQNI Crocknagrogan Ltd NI 226 On-shore wind RO 2013-09-06 2013-09-06 42.2% 66.1% 2026‑03 1,303
R00009SRSC Galashiels WWTW CHP SC 124 Sewage Gas RO 2015-12-07 2015-12-07 62.7% 66.1% 2026‑03 718
G01675HYSC Johnstone Micro-Hydro Scheme SC 59 Hydro FiT 2014-11-24 2014-11-24 61.9% 66.0% 2026‑03 341
R00309NQNI Ventus NI 250 On-shore wind RO 2014-05-16 2014-05-16 37.8% 66.0% 2026‑03 1,445
R00147NQNI farrell NI 250 On-shore wind RO 2012-09-28 2012-09-28 42.2% 65.9% 2026‑03 1,443
R00010RREN Bury CHP at Bury WWTW - A,C,D EN 1,864 Sewage Gas RO 2002-04-01 1990-02-01 50.3% 65.9% 2026‑02 6,146
G01542BWEN Stanley Renewable Energy Limited EN 250 Anaerobic Digestion FiT 2014-04-28 2014-04-28 73.1% 65.8% 2026‑03 1,440
G01825HYSC Crook of Devon HEP SC 500 Hydro None 2016-09-09 2016-09-09 57.6% 65.7% 2026‑03 2,879
R00183RXEN Beighton Microgeneration Project EN 65 Landfill Gas RO 2017-03-29 2017-03-28 58.9% 65.7% 2026‑02 374
R00057RJEN Mayton Wood EN 1,888 Landfill Gas RO 2002-04-01 1996-02-01 69.6% 65.7% 2026‑03 1,898
R01277NQNI SP0847-GP NI 225 On-shore wind RO 2017-12-06 2017-12-06 62.3% 65.6% 2026‑03 1,293
R00001NANI Balcas Timber - C,D NI 3,000 Dedicated biomass RO 2005-04-01 2005-04-01 71.7% 65.6% 2026‑03 17,121
G01630HYSC Camps Reservoir SC 65 Hydro FiT 2014-02-10 2014-02-10 67.9% 65.5% 2026‑04 373
R00177RREN Pyewipe Waste Water Treatment Works EN 2,400 Sewage Gas RO 2008-05-30 2007-09-01 50.3% 65.5% 2026‑04 13,773
G01674HYSC Borla Hydro SC 50 Hydro FiT 2014-12-03 2014-12-03 67.6% 65.3% 2026‑03 286
G01612BWEN Generation X EN 1,067 Dedicated biomass FiT 2014-12-15 2014-12-15 26.4% 65.2% 2026‑04 6,092
G01563HYEN Wendron2 EN 35 Hydro FiT 2019-04-24 2019-04-24 66.8% 65.2% 2026‑02 200