R00201RQEN G01597NWEN : Little Cheyne Court Wind Farm

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2008/2009 (5) 59,800 9.4% * 20,470 20,470
2009/2010 59,800 21.5% 112,369 112,369
2010/2011 59,800 24.3% 127,363 127,363
2011/2012 59,800 26.2% 137,770 137,770
2012/2013 59,800 29.7% 155,392 155,392
2013/2014 59,800 31.3% 164,153 164,153
2014/2015 59,800 24.9% 130,420 130,420
2015/2016 59,800 32.0% 168,274 168,274
2016/2017 (7) 59,800 20.9% * 64,209 55,473
Annual Totals to end Oct-16 164,081155,345
Rolling Load Factor27.0 %
Annual Load Factor to end Oct-1631.2 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.